Design mistakes differ from construction mistakes in one respect: a construction error can be put right, a design error you live with for the life of the facility. The five below are all expensive, all common, and all happen before the first brick is laid.
1. Calculating heat load from floor area instead of operating conditions
This is the root of most of the other problems. Heat load depends on the temperature range, the volume of goods received each day, the temperature of those goods at intake, how often the doors open and the ambient conditions — it does not scale linearly with floor area.
If you under-calculate: the store never reaches temperature, the compressor runs continuously with no rest, and equipment life falls away quickly.
If you over-calculate: capital is wasted, the plant short-cycles and wears, and the temperature inside the store fluctuates as the plant switches on and off.
See more how to calculate cold storage capacity.

2. Floor insulation that does not match the operating temperature range
The floor is the item most often cut back, because it is out of sight and nobody sees it. But in a deep-freeze store, a floor without insulation and without protection against freezing will gradually freeze through, causing heaving and structural cracking.
This is a mistake that is almost impossible to correct once the store is operating — dealing with it means emptying the store, shutting it down and breaking out the floor.
3. Evaporator layout that leaves air unable to reach the whole load
A store can report that it is cold enough on the central gauge while dead zones still exist — places the air does not reach, where the temperature is higher than everywhere else. Goods sitting there are affected and nobody knows.
The usual cause is an evaporator layout drawn without regard to how goods are actually stacked, or a failure to leave the required clearances from the walls, the ceiling and the airflow path. This one can be corrected, but at a cost: moving the evaporators or changing the entire stacking layout.

4. Combining several product groups into one room
This decision usually comes from a wish to save on capital cost, and it does save — in year one. The problems then emerge gradually:
- Every product group has its own optimum temperature and humidity range; combine them and one group always loses out
- With produce, ripening fruit gives off ethylene, ageing leafy vegetables and other sensitive goods prematurely
- Strong-smelling goods taint items that absorb odours readily, such as butter, cheese and chocolate
- You cannot shut a room down when throughput is low — the whole store has to keep running
Dividing into rooms costs more up front but allows several temperature ranges, keeps product groups apart, and lets you shut rooms down when there is less stock.
5. Making no provision for expansion
As a business grows, its cold store has to grow with it. If that is not considered at the design stage, the next expansion means rebuilding most of the system rather than simply adding to it.
Three things to allow for in advance: adjacent floor space to extend the envelope, spare refrigeration capacity at the compressor pack, or room to add another pack, and pipework and a control panel with space for further connections.
Allowing for this at the design stage costs very little compared with rebuilding later.
What all five mistakes have in common
All five happen before construction begins, and all stem from skipping the survey and the calculations and going straight to selecting equipment.
This is also why a quotation issued before anyone has surveyed the site should always be treated with suspicion: without operating data you cannot avoid these five mistakes, however good the equipment.
How to avoid them
- Require the contractor to survey the site and present their heat load calculation before quoting
- Provide complete operating data: product type, throughput, temperature of goods at intake, frequency of movements in and out
- Set out your growth plans for the next 3 to 5 years so the contractor can allow for expansion
- Ask for an evaporator layout drawing showing the intended stacking arrangement, not just a floor plan
- Look again at the floor treatment in the quotation — the item most often cut
Tan Long surveys the site and calculates the heat load from actual operating conditions before proposing a configuration.
Frequently asked questions about cold store design mistakes
Which design mistake is hardest to put right?
Floor insulation that does not match the operating temperature range. In a deep-freeze store, the floor gradually freezes, causing heaving and structural cracking; dealing with it means emptying the store, shutting it down and breaking out the floor — effectively impossible while the store is running.
Why shouldn't heat load be calculated from floor area?
Because heat load depends on the temperature range, the volume of goods received each day, the temperature of those goods at intake and how often the doors open — it does not scale linearly with floor area. Two stores of the same floor area can have very different heat loads.
What is a dead zone in a cold store?
An area the air from the evaporators does not reach, where the temperature is higher than elsewhere. The store still reports that it is cold enough on the central gauge, but goods in that zone are affected and nobody knows.
What is wrong with combining several product groups in one room?
It saves capital cost, but one group always loses out, because each has its own temperature and humidity range. There is also the risk of odour transfer and ethylene effects, and the fact that you cannot shut a room down when throughput is low.
What should be allowed for in advance for expansion?
Adjacent floor space to extend the envelope, spare capacity at the compressor pack or room to add another pack, and pipework and a control panel with space for further connections. Allowing for this in advance costs very little compared with rebuilding later.
How do you avoid these design mistakes?
Require the contractor to survey the site and present their heat load calculation before quoting, provide complete operating data, set out your growth plans for the next few years, and ask for an evaporator layout drawing showing the intended stacking arrangement.
Most of these problems originate at the design stage. Working with a cold storage contractor that does its own design and manufactures its own equipment means discrepancies are caught before anyone reaches site.